Products > Molding process > PCR Two-stage Tire Bulding Machine

PCR Two-stage Tire Bulding Machine

General description : The machine has two stages. Production process (TOS) : 

1. Bead manual loading

2.Position the carcass drum at 1# server station to apply the components (LSSR,Ply#1 and#2。etc.)

3.Stitching

4.Bead set automatically 

5.Turn up by bladder 

6.Position the carcass drum at 2# server station to apply SW 

7.Stitching 

8.Finish carcass 

9.Transfer carcass to second stage manually 

10.Set carcass on shape drum automatically 

11.Position the belt drum at 1# belt server station to apply belt

12.Position the belt drum at 2# belt server station to apply belt 

13.Position the belt drum at SOL server station to apply SOL 

14.Position the belt drum tread server stsation to apply tread 

15.Release package into the transfer ring 

16.shape drum into transfer ring 

17.Shaping 

18.Stitching 

19.Finish one green tire. Build mode are TOS and SOT.